求翻译:The internals of the tower shall be installed after the alignment and grouting of the equipment. The tower plate shall be installed from bottom to top with the manhole opened and the supporters fixed as per drawings and specifications. The foreign materials in the tower shall be removed and the rust on the internal wal是什么意思?![]() ![]() The internals of the tower shall be installed after the alignment and grouting of the equipment. The tower plate shall be installed from bottom to top with the manhole opened and the supporters fixed as per drawings and specifications. The foreign materials in the tower shall be removed and the rust on the internal wal
问题补充: |
|
2013-05-23 12:21:38
正在翻译,请等待...
|
|
2013-05-23 12:23:18
内部的大楼的后须装设的定线和水泥浇注的设备。 该大楼字牌须安装从上到下的沙井的支持者开放和固定为每绘图和规格。 在外国的材料须被除去,该大楼生锈的内部墙刷牙权力之前,安装的大楼的路人。 下一个大楼的托盘不得安装,直到前的1人已被夷平。
|
|
2013-05-23 12:24:58
塔的internals在对准线和填水泥设备以后将安装。 塔板材从底部将安装到上面用出入孔被打开的和根据图画和规格被固定的支持者。 在塔将取消杂质,并且铁锈在内部墙壁力量在塔盘子的设施之前将掠过。
|
|
2013-05-23 12:26:38
塔的内部,须安装后对齐方式和灌浆设备。塔板不得固定按图纸和规格的支持者与打开的沙井到顶部安装从底部。在塔的外国材料须被删除,内部墙壁电源上铁锈刷到塔板安装前。直到前一个已被调配下塔板不得安装。通过板须安装后所有塔盘安装、 验收。在塔的外国材料须删除和审查,然后人孔均须关闭。
|
|
2013-05-23 12:28:18
|
湖北省互联网违法和不良信息举报平台 | 网上有害信息举报专区 | 电信诈骗举报专区 | 涉历史虚无主义有害信息举报专区 | 涉企侵权举报专区